Program Measures

Structurally Deficient Bridges - View Larger Image

Data represented is through at least November 1, 2011 unless otherwise indicated

Projects by Phase - View Larger Image

Data represented is through at least November 1, 2011 unless otherwise indicated

Program Schedule Status - View Larger Image

Data represented is through at least November 1, 2011 unless otherwise indicated

In the Spotlight

3 Year Plan Released
ABP Update
Through January 1, 2012 the MassDOT Accelerated Bridge Program has advertised 166 construction projects with a combined construction budget valued at $1.649 Billion.
Of these 166 advertised construction projects:
  • 127 have already, or will, repair/replace 228 bridges throughout the Commonwealth.
  • 39 are maintenance/preservation projects which provide work to improve the safety of many additional bridges in the Commonwealth.
  • 147 have been awarded to a contractor.
  • 77 have been declared 'substantially complete' by MassDOT (or DCR). ABP Update